Metro Rail Expansion
Project Rendering

As we progress with Metro's Transit Expansion Project, we are excited to share some updates:

  • The NFTA, in cooperation with the FTA, is in the environmental review process for extending rapid transit service along the Buffalo-Amherst-Tonawanda corridor, through UB, and ending at the I-990.
  • The Draft Environmental Impact Statement (DEIS) was released for public comment on July 25, which initiated a 45-day public comment period that ended on September 8.
  • The FTA anticipates releasing the Final EIS/Record of Decision by the end of 2025 or early 2026.
  • 15% of the project's design plans were submitted in April 2025, with an additional 30% expected to advance through 2026.

For additional information, you can also visit: NFTAmetrotransitexpansion